DEPLOYMENT · STEP BY STEP
From the project
to a running fleet.
A deployment with IoT Gateway NG + Edge Manager always follows the same path: prepare at the office, install at the plant and operate remotely. The first gateway sets the pattern; the next ones repeat it.
01 / THE PATH
Four phases.
Only one at the plant.
On-site work is limited to the physical installation. Preparation, commissioning and operation are done from Edge Manager.
- AAT THE OFFICE
Prepare
Scope, Edge Manager, hardware and standard configuration.
Steps 01–04 - BAT THE PLANT
Install
Network boot, identification and system installation.
Steps 05–06 - CREMOTELY
Commission
Configuration, applications and validation with the customer.
Steps 07–08 - DREMOTELY, CONTINUOUSLY
Operate and scale
Monitoring, updates, recovery and replication.
Steps 09–10
02 / THE STEPS
- 01PHASE A · PREPARE
Define the project
At the officeAgree what must be connected, which data is needed and where it must go.
- Machines, PLCs and sensors on each line, and the data you want from them.
- Target systems: monitoring, analytics or business applications.
- Applications that will run on the gateway, your own or third-party, and their compatibility.
- Plant connectivity and the customer’s network policy.
- 02PHASE A · PREPARE
Set up Edge Manager
At the officeEdge Manager does itPrepare the management platform where the whole fleet will live.
- Edge Manager in the cloud or on the customer’s premises.
- One domain per customer, with its networks and devices.
- When the domain is created, its SSH certificate authority is generated.
- When each device is created, its keys and VPN access are generated.
- 03PHASE A · PREPARE
Choose the hardware
At the officeChoose a device that meets the installation’s requirements.
- Recommended: Protectli VP4651 with coreboot and iPXE, which boots over the network.
- Other devices: the base system, resources and boot method are validated.
- Live USB as an alternative when network boot is not available.
- 04PHASE A · PREPARE
Define the standard configuration
At the officeDefine once the pattern that all gateways will follow.
- Versioned configuration, with forms or in JSON.
- Gateway services: data integration, monitoring and backups.
- Industrial applications to deploy on it.
- Saving a configuration and applying it are separate actions.
- 05PHASE B · INSTALL
Boot and identify the gateway
At the plantThe only time you need to be at the plant: mount, connect and boot the device.
- Mount the device and connect it to the plant network.
- Network boot with iPXE, or with Live USB.
- The operator enters a one-time code, generated by Edge Manager, that identifies the gateway.
- 06PHASE B · INSTALL
Install the system
At the plantEdge Manager does itEdge Manager installs and verifies the system, with no manual gateway configuration.
- OpenWrt installed on the gateway’s internal disk.
- Reboot from the internal disk and access check.
- WireGuard VPN connection to the management network.
- 07PHASE C · COMMISSION
Apply the configuration
RemotelyEdge Manager does itThe gateway receives the standard configuration and the applications from Edge Manager.
- Deployment of the services and applications defined in step 04.
- The gateway’s own SSH certificate, issued by the customer’s authority.
- Execution history with the result and logs of each operation.
- 08PHASE C · COMMISSION
Validate with the plant
RemotelyCheck with the customer that everything works as agreed.
- The data reaches the target systems.
- The applications work with the line’s real data.
- The validated configuration becomes the reference.
- 09PHASE D · OPERATE AND SCALE
Monitor and maintain
RemotelyThe fleet is maintained from Edge Manager throughout its whole life cycle.
- Status, health and incidents of each gateway.
- Controlled security updates of the system and the components.
- Backups and recovery: a replacement device recovers its configuration.
- 10PHASE D · OPERATE AND SCALE
Replicate and scale
RemotelyThe next gateway does not start from zero.
- New gateways with the same standard configuration: steps 05 to 07 are repeated.
- New plants or customers: a new domain with the same pattern.
- Configuration improvements are deployed to the whole fleet.
This is the usual path. The scope, timelines and features of each step depend on the project, the available connectivity and the compatibility of the devices and applications.